Showing posts with label 4. Planning a Software Project. Show all posts
Showing posts with label 4. Planning a Software Project. Show all posts

Sunday, March 21, 2010

4.7 Summary

  • Project planning serves two purposes: to set the overall goals or expectations for the project and the overall approach for managing the project, and to schedule tasks to be done such that the goals are met. In overall planning, effort and schedule estimation are done to establish the cost and schedule goals for the project as well as key milestones. Project quality planning and risk management planning establish approaches for achieving quality goals and ensuring that the project does not fail in the face of risks. In the detailed schedule, tasks for achieving each milestone are identified and scheduled to be executed by specific team members such that the overall schedule and effort for different milestones is met.
  • In a top-down approach for estimating effort for the project, the effort is estimated from the size estimate, which may be refined using other characteristics of the project. Effort for different phases is determined from the overall effort using effort distribution data. COCOMO is one model that uses this approach. In a bottom-up approach to estimation, the modules to be built are identified first, and then using an average effort for coding such modules, the overall coding effort is determined. From coding effort, effort for other phases and overall project are determined, using the effort distribution data.

4.6 Detailed Scheduling

The activities discussed so far result in a project management plan document that establishes the project goals for effort, schedule, and quality; and defines the approach for risk management, ensuring quality, and project monitoring. Now this overall plan has to be translated into a detailed action plan which can then be followed in the project, and which, if followed, will lead to a successful project. That is, we need to develop a detailed plan or schedule of what to do when such that following this plan will lead to delivering the software with expected quality and within cost and schedule. Whereas the overall planning document is typically prepared at the start of the project and is relatively static, the detailed plan is a dynamic document that reflects the current plan of the project. The detailed plan is what assigns work items to individual members of the team.

For the detailed schedule, the major phases identified during effort andbschedule estimation, are broken into small schedulable activities in a hierarchicalbmanner. For example, the detailed design phase can be broken into tasks forbdeveloping the detailed design for each module, review of each detailed design,bfixing of defects found, and so on. For each detailed task, the project managerbestimates the time required to complete it and assigns a suitable resource sobthat the overall schedule is met, and the overall effort also matches. In additionbto the engineering tasks that are the outcome of the development process, thebQC tasks identified in the quality plan, the monitoring activities defined in the monitoring plan, and the risk mitigation activities should also be scheduled.

4.5.2 Project Monitoring and Tracking

The main goal of project managers for monitoring a project is to get visibility into the project execution so that they can determine whether any action needs to be taken to ensure that the project goals are met. As project goals are in terms of effort, schedule, and quality, the focus of monitoring is on these aspects. Different levels of monitoring might be done for a project. The three main levels of monitoring are activity level, status reporting, and milestone analysis. Measurements taken on the project are employed for monitoring.

Activity-level monitoring ensures that each activity in the detailed schedule has been done properly and within time. This type of monitoring may be done daily in project team meetings or by the project manager checking the status of all the tasks scheduled to be completed on that day. A completed task is often marked as 100% complete in detailed schedule—this is used by tools like the Microsoft Project to track the percentage completion of the overall project or a higher-level task. This monitoring is to ensure that the project continues to proceed as per the planned schedule.

4.5.1 Measurements

The basic purpose of measurements in a project is to provide data to project management about the project’s current state, such that they can effectively monitor and control the project and ensure that the project goals are met. As project goals are established in terms of software to be delivered, cost, schedule, and quality, for monitoring the state of a project, size, effort, schedule, and defects are the basic measurements that are needed [43, 75]. Schedule is one of the most important metrics because most projects are driven by schedules and deadlines. Only by monitoring the actual schedule can we properly assess if the project is on time or if there is a delay. It is, however, easy to measure because calendar time is usually used in all plans.

Effort is the main resource consumed in a software project. Consequently, tracking of effort is a key activity during monitoring; it is essential for evaluating whether the project is executing within budget. For effort data some type of timesheet system is needed where each person working on the project enters the amount of time spent on the project. For better monitoring, the effort spent on various tasks should be logged separately. Generally effort is recorded through some on-line system (like the weekly activity report system in [57]), which allows a person to record the amount of time spent against a particular activity in a project. At any point, total effort on an activity can be aggregated.

4.5 Project Monitoring Plan

A project management plan is merely a document that can be used to guide the execution of a project. Even a good plan is useless unless it is properly executed. And execution cannot be properly driven by the plan unless it is monitored carefully and the actual performance is tracked against the plan.
 
Monitoring requires measurements to be made to assess the situation of a project. If measurements are to be taken during project execution, we must plan carefully regarding what to measure, when to measure, and how to measure. Hence, measurement planning is a key element in project planning. In addition, how the measurement data will be analyzed and reported must also be planned in advance to avoid the situation of collecting data but not knowing what to do with it. Without careful planning for data collection and its analysis, neither is likely to happen. In this section we discuss the issues of measurements and project tracking.

4.4.4 A Practical Risk Management Planning Approach

Though the concept of risk exposure is rich, a simple practical way of doing risk planning is to simply categorize risks and the impacts in a few levels and then use it for prioritization. This approach is used in many organizations. Here we discuss a simple approach used in an organization [58]. In this approach, the probability of a risk occurring is categorized as low, medium, or high. The risk impact can also be classified as low, medium, and high. With these ratings, the following simple method for risk prioritization can be specified:

4.4.3 Risk Control

The main objective of risk management is to identify the top few risk items and then focus on them. Once a project manager has identified and prioritized the risks, the top risks can be easily identified. The question then becomes what to do about them. Knowing the risks is of value only if you can prepare a plan so that their consequences are minimal—that is the basic goal of risk management.
 
One obvious strategy is risk avoidance, which entails taking actions that will avoid the risk altogether, like the earlier example of shifting the building site to a zone that is not earthquake-prone. For some risks, avoidance might be possible.

4.4.2 Risk Assessment

The goal of risk assessment is to prioritize the risks so that attention and resources can be focused on the more risky items. Risk identification is the first step in risk assessment, which identifies all the different risks for a particular project. These risks are project-dependent and identifying them is an exercise in envisioning what can go wrong. Methods that can aid risk identification include checklists of possible risks, surveys, meetings and brainstorming, and reviews of plans, processes, and work products [45].

Checklists of frequently occurring risks are probably the most common tool for risk identification—most organizations prepare a list of commonly occurring risks for projects, prepared from a survey of previous projects. Such a list can form the starting point for identifying risks for the current project.

4.4.1 Risk Management Concepts

Risk is defined as an exposure to the chance of injury or loss. That is, risk implies that there is a possibility that something negative may happen. In the context of software projects, negative implies that there is an adverse effect on cost, quality, or schedule. Risk management is the area that tries to ensure that the impact of risks on cost, quality, and schedule is minimal. Risk management can be considered as dealing with the possibility and actual occurrence of those events that are not “regular” or commonly expected, that is, they are probabilistic. The commonly expected events, such as people going on leave or some requirements changing, are handled by normal project management. So, in a sense, risk management begins where normal project management ends. It deals with events that are infrequent, somewhat out of the control of the project management, and which can have a major impact on the project.
 
Most projects have risk. The idea of risk management is to minimize the possibility of risks materializing, if possible, or to minimize the effects if risks actually materialize. For example, when constructing a building, there is a risk that the building may later collapse due to an earthquake. That is, the possibility of an earthquake is a risk. If the building is a large residential complex, then the potential cost in case the earthquake risk materializes can be enormous. This risk can be reduced by shifting to a zone that is not earthquake-prone. Alternatively, if this is not acceptable, then the effects of this risk materializing are minimized by suitably constructing the building (the approach taken in Japan and California). At the same time, if a small dumping ground is to be constructed, no such approach might be followed, as the financial and other impact of an actual earthquake on such a building is so low that it does not warrant special measures.
 
It should be clear that risk management has to deal with identifying the undesirable events that can occur, the probability of their occurring, and the loss if an undesirable event does occur. Once this is known, strategies can be formulated for either reducing the probability of the risk materializing or reducing the effect of risk materializing. So the risk management revolves around risk assessment and risk control.

4.4 Risk Management Planning

A software project is a complex undertaking. Unforeseen events may have an adverse impact on a project’s ability to meet the cost, schedule, or quality goals. Risk management is an attempt to minimize the chances of failure caused by unplanned events. The aim of risk management is not to avoid getting into projects that have risks but to minimize the impact of risks in the projects that are undertaken.
A risk is a probabilistic event—it may or may not occur. For this reason, we frequently have an optimistic tendency to simply not see risks or to hope that they will not occur. Social and organizational factors also may stigmatize risks and discourage clear identification of them [19]. This kind of attitude gets the project in trouble if the risk events materialize, something that is likely to happen in a large project. Not surprisingly, then, risk management is considered first among the best practices for managing large software projects [17]. It first came to the forefront with Boehm’s tutorial on risk management [11]. Since then, several books have targeted risk management for software [18, 45].

4.3 Quality Planning

Having set the goals for effort and schedule, the goal for the third key dimension of a project—quality—needs to be defined. However, unlike schedule and effort, quantified quality goal setting for a project and then planning to meet it is much harder. For effort and schedule goals, we can easily check if a detailed plan meets these goals (e.g., by seeing if the last task ends before the target date and if the sum total of effort of all tasks is less than the overall effort goal). For quality, even if we set the goal in terms of expected delivered defect density, it is not easy to plan for achieving this goal or for checking if a plan can meet these goals. Hence, often, quality goals are specified in terms of acceptance criteria— the delivered software should finally work for all the situations and test cases in the acceptance criteria. Further, there may even be an acceptance criterion on the number of defects that can be found during the acceptance testing. For example, no more than n defects are uncovered by acceptance testing.

The quality plan is the set of quality-related activities that a project plans to do to achieve the quality goal. To plan for quality, let us first understand the defect injection and removal cycle, as it is defects that determine the quality of the final delivered software.

4.2 Project Schedule and Staffing


After establishing a goal on the effort front, we need to establish the goal for delivery schedule. With the effort estimate (in person-months), it may be tempting to pick any project duration based on convenience and then fix a suitable team size to ensure that the total effort matches the estimate. However, as is well known now, person and months are not fully interchangeable in a software project. Person and months can be interchanged arbitrarily only if all the tasks in the project can be done in parallel, and no communication is needed between people performing the tasks. This is not true for software projects—there are dependencies between tasks (e.g., testing can only be done after coding is done), and a person performing some task in a project needs to communicate with others performing other tasks. As Brooks has pointed out [16], “... man and months are interchangeable only for activities that require no communication among men, like sowing wheat or reaping cotton. This is not even approximately true of software ....”
However, for a project with some estimated effort, multiple schedules (or project duration) are indeed possible. For example, for a project whose effort estimate is 56 person-months, a total schedule of 8 months is possible with 7 people. A schedule of 7 months with 8 people is also possible, as is a schedule of approximately 9 months with 6 people. (But a schedule of 1 month with 56 people is not possible. Similarly, no one would execute the project in 28 months with 2 people.) In other words, once the effort is fixed, there is some flexibility in setting the schedule by appropriately staffing the project, but this flexibility is not unlimited. Empirical data also suggests that no simple equation between effort and schedule fits well [72].

4.1.2 Bottom-Up Estimation Approach

A somewhat different approach for effort estimation is the bottom-up approach. In this approach, the project is first divided into tasks and then estimates for the different tasks of the project are obtained. From the estimates of the different tasks, the overall estimate is determined. That is, the overall estimate of the project is derived from the estimates of its parts. This type of approach is also called activity-based estimation. Essentially, in this approach the size and complexity of the project is captured in the set of tasks the project has to perform.
 
The bottom-up approach lends itself to direct estimation of effort; once the project is partitioned into smaller tasks, it is possible to directly estimate the effort required for them, especially if tasks are relatively small. One difficulty in this approach is that to get the overall estimate, all the tasks have to be enumerated. A risk of bottom-up methods is that one may omit some activities. Also, directly estimating the effort for some overhead tasks, such as project management, that span the project can be difficult.

4.1.1 Top-Down Estimation Approach

Although the effort for a project is a function of many parameters, it is generally agreed that the primary factor that controls the effort is the size of the project. That is, the larger the project, the greater is the effort requirement. The topdown approach utilizes this and considers effort as a function of project size. Note that to use this approach, we need to first determine the nature of the function, and then to apply the function, we need to estimate the size of the project for which effort is to be estimated.

If past productivity on similar projects is known, then it can be used as the estimation function to determine effort from the size. If productivity is P KLOC/PM, then the effort estimate for the project will be SIZE/P personmonths. Note that as productivity itself depends on the size of the project (larger projects often have lower productivity), this approach can work only if the size and type of the project are similar to the set of projects from which the productivity P was obtained (and that in the new project a similar productivity can be obtained by following a process similar to what was used in earlier projects).

4.1 Effort Estimation

For a software development project, overall effort and schedule estimates are essential prerequisites for planning the project. These estimates are needed before development is initiated, as they establish the cost and schedule goals of the project. Without these, even simple questions like “is the project late?” “are there cost overruns?” and “when is the project likely to complete?” cannot be answered. A more practical use of these estimates is in bidding for software projects, where cost and schedule estimates must be given to a potential client for the development contract. (As the bulk of the cost of software development is due to the human effort, cost can easily be determined from effort by using a suitable person-month cost value.) Effort and schedule estimates are also required for determining the staffing level for a project during different phases, for the detailed plan, and for project monitoring.
 
The accuracy with which effort can be estimated clearly depends on the level of information available about the project. The more detailed the information, the more accurate the estimation can be. Of course, even with all the information available, the accuracy of the estimates will depend on the effectiveness and accuracy of the estimation procedures or models employed and the process. If from the requirements specifications, the estimation approach can produce estimates that are within 20% of the actual effort about two-thirds of the time, then the approach can be considered good. Here we discuss two commonly used approaches.

4. Planning a Software Project

Planning is the most important project management activity. It has two basic objectives—establish reasonable cost, schedule, and quality goals for the project, and to draw out a plan to deliver the project goals. A project succeeds if it meets its cost, schedule, and quality goals. Without the project goals being defined, it is not possible to even declare if a project has succeeded. And without detailed planning, no real monitoring or controlling of the project is possible. Often projects are rushed toward implementation with not enough effort spent on planning. No amount of technical effort later can compensate for lack of careful planning. Lack of proper planning is a sure ticket to failure for a large software project. For this reason, we treat project planning as an independent chapter. Note that we also cover the monitoring phase of the project management process as part of planning, as how the project is to be monitored is also a part of the planning phase.

The inputs to the planning activity are the requirements specification and maybe the architecture description. A very detailed requirements document is not essential for planning, but for a good plan all the important requirements must be known, and it is highly desirable that key architecture decisions have been taken.